Project Description

Holden Drive over Julia Creek

Construction of concrete bridge including installation of precast piles, precast headstock and M-Lock Bridge System, concrete abutments, approach slabs, drainage works, precast parapets and bridge railings

 

Dick Johhnson Drive over Julkia Creek

Construction of concrete bridge including installation of piles and pile caps, concrete abutments and retaining walls, installation of M-Lock Bridge System, approach slabs, drainage works, precast parapets and bridge railings