Flemington Station

Project Facts:

Name: Flemington Station
Location: Flemington
Client: Laing O'Rourke
Commencement: February 2016
Duration: 6 Months

Project Description:

Laing O’Rourke engaged Talis Civil to commence concrete works at their newly awarded Flemington Station Project on the last working day of 2015 with works to start first week back in 2016.
Talis was engaged to undertake all the excavation, shoring, form reo and pouring of three new station headstock structures two of which were directly positioned on the existing station platform surrounded by active rail platforms with hundreds of train movements every day.
Through hard work, long hours and numerous rail shutdown works Talis was able to deliver each of the four structures in time for Laing O’Rourke’s critical lifts.